Timescales

Key project dates*:
- December 2024 – co-funding secured from Nottinghamshire CC
- April 2025 - demolition and asbestos removal, subject to planning
- February 2026 - award of main works contract
- October 2027 – scheduled build completion
- January 2028 – tenant fit out and full operational completion
- Spring 2028 – open
*All dates are a guide and are subject to change
As we move through the project, we understand the public will have questions about the project. Some of which, we won't have the answers to yet as they could be hinged on the final design.
View our latest Q&A document below.
This will be updated as the project progresses.