Bellamy Road, Mansfield (completed 2011)

The council started building affordable housing again in 2010 with a development of 43 new homes across the Bellamy Road estate.

Scheme details

Images

Scheme details

The development of family houses consisted of:

  • 9 x 4 bed 6 person houses: and
  • 34 x 3 bed 5 person houses

These were built across four brownfield sites at Colston Court and on Bellamy Road itself.  Half of the properties have solar panels fitted and the other half have ground source heat pumps installed.  All of the properties achieved Code Level 4 of the Code for Sustainable Homes.

The contractor employed by the council was William Davis Ltd.  They started work in March 2010 and completed in October 2011.

The total cost of the scheme was £4,309,646 and the council received grant from the Homes and Communities Agency of £2,154,823 towards the cost of works.

The development won the Best Large Housing Development Award in the East Midlands LABC awards in 2012.